Process for Self-Laying New Water Mains and Services

Process for self-laying new mains and services

If you’re extending or building a new property, you can ask us to design and build the new water mains and service pipes.

Alternatively, you can choose an accredited self-lay provider (SLP) to complete some or all of this work. SLPs may offer more flexible timescales and the option to install multiple utilities, which could save you time and money.

Accreditation

SLPs must complete the work under the Codes for Adoption and be accredited by the Water Industry Registration Scheme (WIRS).

Find a list of approved SLPs.

Cost

Our charging arrangements allow you to estimate application, design and other charges relating to the construction of your new water mains. We update these on 1 April each year.

Overview of the process

Graphic describing the process for self-laying new water mains

Step 1: Submit a pre-planning enquiry

The sooner we know about your development, the better. Once you’ve submitted your point of connection application, we’ll issue you with a point of connection (POC) report within 28 days. The report is valid for 12 months. You can use this to help with your planning permission and project planning.

Find out more about pre-planning enquiries.

Step 2: SLP submits application and pays fee

Find out how and when to apply for your mains and service connection.

Once we’ve received your full application, we’ll send you a quote within 28 to 42 days. You can choose whether you’d like us or your SLP to complete the technical design of your new main system. Our quote will include both options.

Your quote is valid for six months. Please sign and return it by email to developer.services@thameswater.co.uk. Please make the payment before your quote expires. We update charging arrangements on 1 April each year.

Step 3: Design the water main system

If your SLP is designing your mains, we’ll need to check these. You’ll then liaise with the SLP to discuss next steps.

If we’re designing your mains, we’ll contact you once you’ve accepted the quote to arrange a commencement meeting. At this meeting, we’ll confirm:

Step 4: Sign adoption agreement

The WMAA is a legal agreement between us, the SLP and the developer/land owner for the completion of works. This need to be signed by all parties before works commence on-site.

The agreement includes:

Step 5: Construct the mains

Your SLP will construct the new main system, according to the technical designs and Design and Construction guide.

A 10 day notification will need to be submitted before any construction of mains can start.

Step 6: Commissioning and connecting the mains

Commissioning

Before connecting the new main, it must be pressure tested and chlorinated. Water samples must also be taken for bacteriological testing. It’s not necessary for one of our engineers to be on site for this, but we may conduct audits to ensure compliance.

When you receive the results, you must send them to us for review within one day.

The total time taken to commission the new main is seven days. It must be completed within 14 days of the sample being taken.

Connecting

A Thames Water engineer must be on site to witness the connection. This is to ensure EUSR accredited professionals are completing the works.

You’ll need to submit a safe control routine mains connection form seven days before the connection takes place.

Step 7: Vesting the new mains

Once the new mains have been commissioned, we will adopt (vest) the assets. When the connection is complete, the SLP must tell us within one day. We’ll then issue a vesting certificate within five days. The SLP will also need to submit an updated as-laid drawing showing that the main is live.

You and the SLP will be responsible for rectifying any defects in the mains for 12 months following the commissioning.

Step 8: Completing service connections