Planning Your Works Under the New Roads and Street Works Act

Planning your works

Process

We follow the process set out in the New Roads and Streetworks Act 1991 (NRSWA) and its code of practice. The code of practice has several stages and each stage must be complete to progress to the next. Here’s everything you need to know if you’re a Highway Authority carrying out roadworks in a street.

Planning your work

If you’re a qualifying highway authority as defined in the New Roads and Street Works Act 1991 (NRSWA) and carrying out road works or major highway works in the street, we’ll share the costs of diverting our assets if they’re affected by your work. We’ll also share the costs of diverting our assets in streets if you are a bridge authority carrying out major works on a bridge or a transport authority carrying out major works.

Please refer to the guidelines for working near our pipes if you’re:

Checking the location of water mains and sewers

In appendix C2 of ‘Measures necessary where apparatus is affected by Major works (diversionary works)’ Code of practice that accompanies the NRSWA you’ll need to check if we have any pipes or other equipment near your planned work. Learn more about where our pipes are.

Request a budget estimate

To request your C3 budget estimate, please email our Development Control team (Devcon.team@thameswater.co.uk), stating the work you’re planning and how close it is to our assets. If there will be an impact on our assets, we will provide you with a budget estimate, as per section C3 of the Act.

We need to know about your scheme in its entirety. We only provide a quote for one scheme, rather than a range of options. There’s a charge for asking for a re-estimate of the same scheme later.

You can also put your request in writing on a letter headed ‘C3 budget estimate request’ and post it to:

Thames Water Development Planning, Maple Lodge Sewage Treatment Works, Denham Way, Rickmansworth, WD3 9SQ

Please include the following information:

What we’ll do

If we have everything required, we’ll carry out a high-level review and produce a budget estimate for you. We aim to complete this within 20 days, however if the scheme is complex or affects more than one asset it may take longer, we will discuss this with you on an individual case basis.

If there’s no need to divert our pipes, we’ll provide a protection letter, detailing how to avoid damaging our equipment during your work. We may ask for further details or direct you to another team.

This initial budget estimate is free. We’ll also include the fee that you’ll need to pay to initiate the C4 detailed estimate.

Next steps

After we have provided a C3 budget estimate, if you wish to proceed to the C4 stage, then please get in contact with the engineer that you’ve been corresponding with.