Disconnections for Clean Water Developments
Disconnections
If you no longer require the existing water supply for your new development — if you’re demolishing a property or converting multiple properties for example — we can arrange for it to be disconnected.
We’ll remove the point connecting your site to our water main, which is usually within the road. You’ll need your plumber to remove the pipework within your property boundary. Disconnections are permanent so we’ll need authorisation from the registered owner.
If you need to restore the water supply later, you’ll have to pay for a new water connection.
If you need your existing supply disconnecting and a new one installed, please refer to our new or replacement connection section. If you’re unsure whether a disconnection is required, please contact us.
The disconnection process
If you’d like to permanently disconnect your existing water supply, you’ll need the following:
- The applicant’s full name, contact number and email address.
- Address of site where you would like the permanent disconnection.
- Details of the supply you are requesting to be disconnected.
- Permission from the relevant neighbours if you have a shared water supply.
- Site location plan.
Apply for a disconnection
To apply, please download the form and email it back to us.
- Disconnect your water supply application form (pdf | 497.3 KB)
Step 1 - You submit an application
We’ll need your contact information and the following:
- The address of where you’d like the disconnection.
- Details of the supply you want disconnected
- A site location plan.
We’ll disconnect free of charge – but if you ever need the water supply again, you’ll need to pay for it to be installed.
If you’re a commercial customer, please contact your retailer or visit the Open Water website.
Step 2 - We mark up
We’ll call you to arrange a mark-up appointment and to locate the supply and identify any traffic management needs. We’ll call within seven days of receiving your application and we aim to attend within 14 days of talking with you.
Step 3 - We disconnect
After the mark-up, we aim to carry out the disconnection within 21 days. Once the mark-up has been carried out, we’ll speak with the local authority and other bodies responsible for roads and traffic, such as Transport for London and bus companies. This can limit how and when we can work by restricting hours, or by requiring road closures which involve a notice period.
We work with the relevant authorities to carry out the work as efficiently as possible, but disconnections often take longer than 21 days. Learn more about traffic management.