Disconnecting Your Water Supply
Disconnecting your water supply
As part of renovation, demolition or extension work, you may need to disconnect your water supply. Here’s everything you need to know and what you need to do.
What’s involved?
If you don’t need the water supply for your property, we can arrange for it to be disconnected. We’ll remove the point connecting you to our water main (usually within the road) and you’ll need a plumber to remove the pipework within your property boundary.
If you’re unsure if you need a disconnection, please contact us.
Please note: The registered owner needs to give authorisation for a permanent disconnection.
If you need your existing supply disconnecting and a new one installed, please refer to our new or replacement connection section.
Here’s the process for getting your supply disconnected:
If you’d like to permanently disconnect your existing water supply, you’ll need the following:
- The applicant’s full name, contact number and email address
- Address of site where you would like the permanent disconnection
- Details of the supply you are requesting to be disconnected
- Permission from the relevant neighbours if you have a shared water supply
- Site location plan
Apply for a disconnection
To apply, please download the form and email it back to us.
- Disconnect your water supply application form (pdf | 497.3 KB)
Step 1 - Submit an application
We’ll need the following information:
- Contact information.
- The address to be disconnected.
- Details of the supply to be disconnected.
- A site location plan.
Disconnecting your supply is free, but if you ever need the water supply again, you’ll have to pay for it to be installed. To find out more please call us on 0800 009 3921.
If you’re a commercial customer please contact your retailer or visit the Open Water website.
Step 2 - We mark-up
We’ll call you to arrange a ‘mark-up’ appointment within seven days of you submitting your application. At this appointment, we’ll locate the supply and identify any traffic management needs and it should happen within 14 days of talking with you.
Step 3 - We disconnect
After the mark-up, we aim to carry out the disconnection within 21 days. Once the mark-up has been carried out, we’ll speak with the local authority and other bodies responsible for roads and traffic, such as Transport for London and bus companies.
This can limit how and when we can work by restricting hours, or by requiring road closures which involve a notice period. We work with the relevant authorities to carry out the work as efficiently as possible, but disconnections often take longer than 21 days.