Developing Over or Near Sewers

Developing over or near sewers

We’re responsible for taking care of our sewerage network in line with Section 94 of the Water Industry Act 1991.

It may not be permitted to construct new properties over sewers or drains, we would prefer that the public sewer be diverted if possible. Find out more about diverting a sewer.

Build over agreements are required for any building works to existing properties within 3 metres of a public sewer, or within 1 metre of a public lateral drain. This is to prevent damage to the sewer network, and ensures we have suitable and safe access to carry out maintenance and repairs.

For more information about build over agreements, please see our build over technical specifications and example drawings.

Apply to develop over a sewer

If you’re building over a sewer with the internal diameter of 375mm, it’s likely to be considered a class 3 application. Below you’ll find some helpful frequently asked questions about class 3 build over applications.

How long do class 3 applications take?

From application, to construction, can take 3 to 9 months or longer. The time varies greatly between applications, depending on the complexity of the build over.

The steps are outlined below:

  1. You apply online
  2. We review and respond to your application within 21 days
  3. You call us to arrange your pre-construction survey
  4. Your deed of easement is registered
  5. We issue your consent to commence
  6. You complete construction
  7. You call us to arrange your post-construction survey – which is usually completed within 21 days
  8. We issue your agreement

Why are class 3 applications more expensive?

Class 1 and 2 build over agreements (for sewers 375mm and under) are simpler.

These applications are usually less complex than class 3 agreements, which means they usually take our team less time to complete.

Instead of CCTV surveys used in class 2 applications, an engineer may conduct a survey of the sewer on site. A deed of easement is also required for class 3 applications.

What additional information is required?