Building Over Sewers or Public Drains

Building over sewers or public drains

You must get a build over agreement before starting any construction work. Retrospective agreements may not be approved if our pipework was not properly protected, as per our specifications. Without an agreement, you may have issues selling your property later.

Before you begin your build over agreement application, you’ll need to know:

Application process

Before you begin: application preparation

There are three classes of build over agreement, depending on the size of the public sewer or lateral drain you wish to build over - see the FAQ section below for more details.

You’ll need to supply essential documents with your application. The plans supplied by your architect will likely be different to those supplied for building regulations purposes. Please share the below examples with your architect or structural engineer to ensure they provide what we need.

For all three classes, you’ll need to upload the following:

Location plan

Existing and proposed building and drainage layout plan

Sectional drawing showing proposed foundations and sewer(s)

Other documents may be needed, in addition to those listed above:

Step 1: apply and pay your fees

Once you’ve gathered everything you need, please complete your build over application. You can then pay for your build over application.

You’ll need to know:

It’s vital that you upload the correct documents and information, otherwise your application will be put on hold, which may result in delays.

Once you’ve applied you’ll be asked to make your payment.

Step 2: we’ll process your application

Our technical team will review your application within 21 days of submitting your application and making your payment.

If we need any further information, your application could be delayed. To avoid this, please make sure you submit everything that we’ve asked for in the ‘application preparation’ section above.

Class 1 applications only (for sewers up to 175mm)

If your application is approved, we’ll issue your build over agreement and your construction can commence. This is the end of your application process. If we couldn’t approve, we’ll be in touch with more information.

Step 3: pre-construction surveys

For class 2 applications (for sewers from 176mm to 375mm)

We’ll be in touch to arrange a CCTV survey, which usually takes place within 10 days. It will assess the condition of the sewer to find out if any repair work is needed before you start construction.

For class 3 applications (for sewers over 375mm)

We’ll be in touch to arrange an engineer to assess the condition of the sewer, which usually takes place within 10 days. We’ll check if any repair work is needed before you start construction. At this stage, other legal agreements will be put into place.

For both application types, providing our survey doesn’t show any issues with the sewer, we’ll send you a formal notice allowing you to start construction works.

Step 4: construction work takes place

You can undertake your construction work as per your agreement with Thames Water.

Step 5: post-construction surveys

For class 2 applications (for sewers from 176mm to 375mm)

You’ll get in touch with us to arrange a CCTV survey, which usually takes place within 10 days of your call. We’ll assess the condition of the sewer to make sure no damage occurred during construction.

For class 3 applications (for sewers over 375mm)

You’ll get in touch with us to arrange an engineer to assess the condition of the sewer to make sure no damage occurred during construction. This usually takes 10 days from your call.

Step 6: build over agreement issued

Once we’ve approved the post-construction survey, we’ll issue your build over agreement.

Once you’ve received your build over agreement, keep this for your records as it may be needed when you sell the property.

Downloads

Frequently asked questions

Key terms

How much does a build over agreement cost?

These charges are updated on 1 April each year.

What does the application fee cover?

The application fee covers:

Class 2 applications also include pre and post-construction CCTV surveys.

Class 3 applications also include two pre and post-construction surveys conducted by one of our approved contractors, impact assessments (where required) and additional legal work.

Is there a discount for disabled applicants?

Applicants with a disability receive a £130 discount on their build over agreement application by submitting proof of entitlement to disability benefit. For example, a letter from the Department of Works and Pensions or a Blue Badge.

Where can I find the build over technical specifications?

View our build over technical specifications.

Applying for a retrospective build over agreement

Complete the build over agreement application and tick the box for a retrospective application. For all classes of application, you’ll need a CCTV or on-site survey to check that no damage has occurred to the sewer during construction.

Can I divert the sewer?

There are two ways to apply for a sewer diversion, depending on the complexity of your requirements.

Build over: minor sewer diversions

For short diversions to smaller sewers required for domestic extensions or home improvements, you may be able to apply for a minor diversion. Your proposal must meet the following criteria:

A CCTV survey will be required before construction begins, to assess the condition of the sewer, and after it’s been completed, to ensure it’s been constructed to the agreed specifications and no damage has occurred. A refundable cash deposit of £2,000 is required and will be refunded once the completed diversion has been inspected by Thames Water and found to be in a satisfactory condition.

To apply for a minor sewer diversion, complete the build over application online.

Sewer diversions

If you do not meet the minor sewer diversion, you’ll need to complete a full sewer diversion application.

Read more about the process and apply on our diverting a sewer page.